Control, on paper, where it can be audited.

A construction manager is only worth the documents it produces. Here is what gets written, how often, and against which standards.

Technical references

What the work is checked against

Photovoltaic plant

  • IEC 62446-1 — commissioning tests, documentation and inspection
  • IEC 62548 — photovoltaic array design
  • IEC 61215 and IEC 61730 — module qualification and safety
  • IEC 60364-7-712 — low-voltage installations, PV supply systems

Wind plant

  • IEC 61400-1 — design requirements
  • IEC 61400-24 — lightning protection
  • Turbine supplier erection and commissioning procedures

Electrical and grid

  • IEC 61439 — low-voltage switchgear assemblies
  • GNERC grid code and the GSE connection conditions for the project
  • Protection settings agreed with GSE before energisation

Civil and general

  • Georgian technical regulations on construction and building safety
  • Georgian labour-safety legislation
  • HSE procedures aligned to the ISO 45001 framework

These are the standards the work is checked against. Where ENGIA Green holds a certification in its own name it is stated on the company page with the certificate number and the certifying body; where it does not, the site says only that the procedure is aligned to the framework.

Site documents

What gets written

DocumentFrequency
Daily site reportDaily
Inspection and test plan — hold point recordsPer activity
Non-conformance report and registerAs raised
Request for information logAs raised
Photographic progress recordWeekly
Progress and programme reportMonthly
Payment certificateMonthly
HSE audit and incident registerMonthly, and on event
Permit-conditions registerLive
Punch listFrom pre-handover
As-built and warranty dossierAt handover

Reporting

Who hears what, and when

The owner gets a monthly report against the baseline programme with the slippage stated rather than smoothed. Where the project is financed, the lender’s technical advisor gets the same pack on the same date — not a different one.

Anything that threatens the commercial operation date is escalated when it is identified, not at the next monthly. In practice that means grid outage windows, long-lead equipment and permit conditions, which between them account for most of the slippage on Georgian renewables construction.

Two cadences, deliberately different: progress is reported to the owner monthly, while the capacities and dates published on this site are revised quarterly, in step with NEXT Energy. A public page that moved every month would be noise.

The one number worth watching. Non-conformances raised, and how many are still open. A site with no NCRs is not a well-run site; it is an unsupervised one.