Four plants, 67.05 MW installed.

All four are owned by NEXT Energy subsidiaries. Two mandates are contracted, two are expected and labelled as such. Capacity is MW DC for solar and nameplate for wind; grid export in MW AC is on every card.

Programme

Where each plant sits

Scroll the chart sideways →

2026Q2Q3Q42027Q2Q3Q42028Q2Udabno Solar PV6.4 MWp · 5 MW ACOCT 2026Iliatsminda Solar PV32.9 MWp · 26 MW ACDEC 2027Kutaisi Solar PV5.25 MWp · 3.5 MW ACDEC 2027Kutaisi Wind22.5 MW nameplateProgramme not issuedTODAY 25 SEP 2026
Elapsed Remaining Commercial operation Ready to build Today

The filled portion of each bar is time elapsed against the construction window. It is not a measure of physical progress, and it should not be read as one — progress against the programme is reported monthly to the owner, not published here.

Detail

Four plants

In construction

Udabno Solar PV

The first NEXT Energy plant to reach commercial operation, and the reference project for everything behind it. Construction began in May 2026 and is substantially complete; the plant is in the grid-works and commissioning window.

Owner / SPV
Georgian Solar Company LLC
Development partner
Georgian Energy Development Fund (GEDF)
Installed capacity
6.4 MWp
Grid export
5 MW AC
Location
Udabno, Sagarejo — Kakheti
EPC contractor
THE OHM Georgia
ENGIA Green mandate
Contracted
Construction window
May 2026 – Oct 2026
Pre-construction

Iliatsminda Solar PV

The largest project in the near-term programme, and the one that sets the resourcing plan for 2027. It runs to the same schedule as Kutaisi Solar, so procurement, mobilisation and supervision are planned as a single 2027 campaign rather than two independent sites.

Owner / SPV
Qiziki Solar LLC
Development partner
OHM Energy LLC
Installed capacity
32.9 MWp
Grid export
26 MW AC
Location
Iliatsminda, Sighnaghi — Kakheti
EPC contractor
THE OHM Georgia
ENGIA Green mandate
Contracted
Construction window
Mar 2027 – Dec 2027
Ready to build
November 2026
Pre-construction

Kutaisi Solar PV

Co-located with Kutaisi Wind. The two plants sit behind one 110/35 kV connection carrying 26 MW in total, which means one set of grid works, one mobilisation and one commissioning sequence rather than two.

Owner / SPV
Aia Wind LLC
Development partner
GURIS Renewables LLC
Installed capacity
5.25 MWp
Grid export
3.5 MW AC
Location
Chognari, Terjola — Imereti
ENGIA Green mandate
Expected — not yet contracted
Construction window
Mar 2027 – Dec 2027
Ready to build
November 2026
Programme not issued

Kutaisi Wind

Onshore wind, co-located with Kutaisi Solar behind the shared connection. Turbine erection is a different discipline from PV — crane pads, heavy-lift access and a weather-dependent lift window — and the supervision plan is scoped separately.

Owner / SPV
Aia Wind LLC
Installed capacity
22.5 MW
Location
Terjola — Imereti
ENGIA Green mandate
Expected — not yet contracted

Capacities and dates on this page match the NEXT Energy pipeline at nextenergy.ge and are revised on the same quarterly cycle. If the two ever disagree, the owner’s page governs and this one is out of date — tell us.

Terjola

One connection, two plants

Kutaisi Solar and Kutaisi Wind sit behind a single 110/35 kV connection: 27.75 MW installed — 5.25 MWp of modules and 22.5 MW of turbine — exporting through 26 MW AC. Grid capacity is the scarce input in Georgian development, and a connection carrying both wind and solar runs at a higher load factor than either would alone.

For a construction manager it means one mobilisation, one set of civil and electrical works, one energisation sequence with GSE and one commissioning campaign — but two different disciplines on the same site at the same time, which is a supervision problem worth planning for rather than discovering.