In construction
Udabno Solar PV
The first NEXT Energy plant to reach commercial operation, and the reference project for everything behind it. Construction began in May 2026 and is substantially complete; the plant is in the grid-works and commissioning window.
- Owner / SPV
- Georgian Solar Company LLC
- Development partner
- Georgian Energy Development Fund (GEDF)
- Installed capacity
- 6.4 MWp
- Grid export
- 5 MW AC
- Location
- Udabno, Sagarejo — Kakheti
- EPC contractor
- THE OHM Georgia
- ENGIA Green mandate
- Contracted
- Construction window
- May 2026 – Oct 2026
Pre-construction
Iliatsminda Solar PV
The largest project in the near-term programme, and the one that sets the resourcing plan for 2027. It runs to the same schedule as Kutaisi Solar, so procurement, mobilisation and supervision are planned as a single 2027 campaign rather than two independent sites.
- Owner / SPV
- Qiziki Solar LLC
- Development partner
- OHM Energy LLC
- Installed capacity
- 32.9 MWp
- Grid export
- 26 MW AC
- Location
- Iliatsminda, Sighnaghi — Kakheti
- EPC contractor
- THE OHM Georgia
- ENGIA Green mandate
- Contracted
- Construction window
- Mar 2027 – Dec 2027
- Ready to build
- November 2026
Pre-construction
Kutaisi Solar PV
Co-located with Kutaisi Wind. The two plants sit behind one 110/35 kV connection carrying 26 MW in total, which means one set of grid works, one mobilisation and one commissioning sequence rather than two.
- Owner / SPV
- Aia Wind LLC
- Development partner
- GURIS Renewables LLC
- Installed capacity
- 5.25 MWp
- Grid export
- 3.5 MW AC
- Location
- Chognari, Terjola — Imereti
- ENGIA Green mandate
- Expected — not yet contracted
- Construction window
- Mar 2027 – Dec 2027
- Ready to build
- November 2026
Programme not issued
Kutaisi Wind
Onshore wind, co-located with Kutaisi Solar behind the shared connection. Turbine erection is a different discipline from PV — crane pads, heavy-lift access and a weather-dependent lift window — and the supervision plan is scoped separately.
- Owner / SPV
- Aia Wind LLC
- Installed capacity
- 22.5 MW
- Location
- Terjola — Imereti
- ENGIA Green mandate
- Expected — not yet contracted